street-32607__340I swear I wrote about this somewhere before, but I can’t find it.  Anyhow, KeysNet/Reporter/KeyNoter has a story up about the C-905 bike lane project on their fancy, new website – www.flkeysnews.com.

This is the project where the contractor narrowed the lanes on C-905 by about six inches in order to install the new bike path.  As a result, the speed limit had to be lowered from 55 mph to 45 mph.  Oops.

It sounds like the county is going to settle.  They get $200,000 knocked off their bill.

How did this happen?  How did the county get so far into the project without realizing that the road wasn’t wide enough?

I understand mistakes happen, but these snafus are a regular thing.  At least this particular project didn’t go way over budget – as far as I know.  Things are bad and seem to be getting worse.

This entry was posted in BOCC, Monroe County, Paving. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s